Predominantly, for management of which one of the following resources is the critical path method (CPM) used as one of the health administration techniques-

Correct Answer: Time
Description: The longer path of the network is called critical path .If any activity along the critical path is delayed,the entire project will be delayed (refer pgno:872 park 23 rd edition)